There will be 4,411 families are affected by this project. The project is now completed 70%, the compensation process is far from the construction, 20.4% completed. It's planned to finish by the end of 2021.
The project is expected to have a direct impact on 26 villages in three provinces: Luang Prabang, Oudomxay and Xayaburi, with an estimated 840 households (9,974 people).
Laos-China Railway project is 70% completed, while the compensation’s paid to affected people is 20.4% (369 billion Kip) of total amount 2,492 billion Kip.